On-Going Projects - The Grove Phase 2

A. Project Details

  • Project Name : The Grove Phase 2a, Sub-structure Work Package
  • Project Location : C-5 Avenue Brgy. Ugong Pasig City
  • Project Owner : Rockwell Land Corporation

    Performance Period
  • Date of Award and Contract Date – 3  February 2012
  • Possession of Site and Commencement of the Works – 2  January 2012
  • Contract Completion –December 31, 2012

B. Project Details

  • Project Name : The Grove Phase 2B-Podium CDEF and Tower CD
  • Project Location : C-5 Avenue Brgy. Ugong Pasig City
  • Project Owner : Rockwell Land Corporation

    Performance Period
  • Date of Award and Contract Date – ------
  • Possession of Site and Commencement of the Works – 01 March 2013
  • Contract Completion –  April 2015


Project Status as of August 25, 2014

Our greatest weakness lies in giving up. The most certain way to succeed is always to try just one more time. And continuously reached our aims no matter how hard, no matter how tough, taking risk is a must, and various problems are not hindrances to reach our goal and that is to meet the target schedule.

Hours, days, months are fastly moving, from establishing of control points to construction of mat foundation and now towers were built and structural work is nearly completed. The complicated design of Podium area mainly on fourth floor level has now overcome. It only proves that nothing is impossible once for those who have positive attitudes.

The main focus of operation group right now has shifted to various architectural works. Firstly, spray crete works, one of the major activity on-site which contribute a big accomplishment of the project, presently Tower C & D has now on their final floor level (37th floor) including also their masonry works at core services.

Meanwhile, interior fit-out work for two towers are simultaneously moving, Tower C & D   has now barely complete the ground floor level to eight floor level  and ground floor level to 12 floor level respectively. Another scope of works that gives priorities by the operation group is the application of waterproofing materials since this is the first step prior for completion of floor finishes and were building water tightness is dependent.

The over-all accomplishment of the project is now 96.00% for Grove Phase 2a and 58.00% for Grove Phase 2b with running total of 7,800,000 man-hours without any loss time accident.

 

On-Going
grove2a_140825_01
grove2a_140825_...
Image Detail Image Download
grove2a_140825_02
grove2a_140825_...
Image Detail Image Download
grove2a_140825_03
grove2a_140825_...
Image Detail Image Download
grove2a_140825_04
grove2a_140825_...
Image Detail Image Download
grove2a_140825_05
grove2a_140825_...
Image Detail Image Download

 

Display Num